基于?分析的转油站系统用能薄弱环节辨识
Identification for the Energy Use Weak Link in Oil Transfer Station System Based on Exergy Analysis
浏览(1304) 下载(3)
- 引用格式:
-
吴浩,于淳光,马国宇,吕莉莉,解红军,成庆林,刘扬.基于?分析的转油站系统用能薄弱环节辨识[J].天然气与石油,2019,37(1):7-14.doi:10.3969/j.issn.1006-5539.2019.01.002
Wu Hao,Yu Chunguang, Ma Guoyu,Lü Lili,Xie Hongjun,Cheng Qinglin.Identification for the Energy Use Weak Link in Oil Transfer Station System Based on Exergy Analysis[J].Natural Gas and Oil,2019,37(1):7-14.doi:10.3969/j.issn.1006-5539.2019.01.002
- DOI:
- 10.3969/j.issn.1006-5539.2019.01.002
- 作者:
- 吴 浩1 于淳光2 马国宇3 吕莉莉1 解红军1 成庆林2 刘 扬2
Wu Hao1,Yu Chunguang2, Ma Guoyu3,Lü Lili1,Xie Hongjun1,Cheng Qinglin2
- 作者单位:
- 1. 中国石油规划总院,2. 东北石油大学提高采收率教育部重点实验室,3. 中国石油北京油气调控中心
1. China Petroleum Planning and Engineering Institute; 2. NEPU Key Laboratory for Enhancing Oil Recovery of the Ministry of Education, Daqing, Heilongjiang; 3. Beijing Oil & Gas Transportation Center
- 关键词:
- 转油站系统;?分析方法;用能薄弱环节;加热炉;节能降耗
Oil transfer station system;Exergy analysis;Energy use weak link;Heating furnace;Energy saving and consumption reduction
- 摘要:
-
依据㶲分析基本理论,对大庆油田某油气集输系统进行了用能薄弱环节分析与辨识。通过研究集输系统物流、㶲流分布情况,将系统划分为管网和转油站两个子系统,确定转油站子系统全年平均效率为19.41% ,管网子系统全年平均㶲效率为72.98% 。根据计算结果对转油站子系统各用能单元㶲损分布情况进一步分析,得出外输泵及掺水泵㶲损占比较小,加热炉为主要用能损耗单元,其㶲损系数为84.3 ,应做为系统用能改进的主要单元。
According to the theory of exergy analysis, the energy use weak link of oil & gas gathering system in Daqing was analyzed and revealed.Through the logistics and exergy distribution analysis of oil transfer station system, the system was divided into two subsystems: the pipe network and the oil transfer station.And the annual average exergy efficiency of oil transfer station was 19.41%, and that of the pipe network was 72.98%.According to the calculation results, further analysis was made on the distribution of loss in each energy consumption unit of oil transfer station.The loss of oil pump and water pump was less.The heating furnace whose coefficient of exergy loss was 84.3% was the main energy loss unit,and the loss of heat transfer process, cooling process and combustion reaction process was larger.It is necessary to improve the heating furnace efficiency or replace it so as to realize energy saving and consumption reduction of oil gathering system.