油气管道定向钻穿越“多接一”回拖的难点与应对
Challenges and countermeasures of managing multiple connections-pullback in horizontal directional drilling of oil and gas pipelines
浏览(623) 下载(28)
- 引用格式:
-
赖思宇,田延彬,秦政先,刘雪梅,向玉琪.油气管道定向钻穿越“多接一”回拖的难点与应对[J].天然气与石油,2023,41(6):38-43.doi:10.3969/j.issn.1006-5539.2023.06.006
LAI Siyu, TIAN Yanbin, QIN Zhengxian, LIU Xuemei, XIANG Yuqi.Challenges and countermeasures of managing multiple connections-pullback in horizontal directional drilling of oil and gas pipelines[J].Natural Gas and Oil,2023,41(6):38-43.doi:10.3969/j.issn.1006-5539.2023.06.006
- DOI:
- 10.3969/j.issn.1006-5539.2023.06.006
- 作者:
- 赖思宇1 田延彬2 秦政先1 刘雪梅1 向玉琪1
LAI Siyu1, TIAN Yanbin2, QIN Zhengxian1, LIU Xuemei1, XIANG Yuqi1
- 作者单位:
- 1. 中国石油工程建设有限公司西南分公司, 四川 成都 610041; 2. 河北华元科工股份有限公司, 河北 廊坊 065001
1. CPECC Southwest Company, Chengdu, Sichuan, 610041, China; 2. Langfang Huayuan Mechanical & Electrical Engineering Co., Ltd., Langfang, Hebei, 065001, China
- 关键词:
- 定向钻;“多接一”;回拖
Directional drilling; Multiple connections; Pullback
- 摘要:
随着定向钻穿越技术的广泛应用,“多接一”(主要指“几十接一”形式)回拖方式对解决定向钻工艺受回拖场地限制有重要意义,但“多接一”回拖方式的运用同样存在不少限制条件。通过对工程实例的分析对比,总结出“多接一”回拖方式和常规定向钻一次回拖的差异和技术难点,并提出应对措施。“多接一”回拖方式适宜在基岩等稳定性较好的地层条件下应用。各项工序之间必须紧密衔接,尽可能缩短回拖暂停时间,以保证整个施工过程高效顺利完成。结合铺管船和支撑架等发送方式,定向钻“多接一”回拖方式值得推广应用。
With the wide application of horizontal directional drilling technology, the method of multiple connections-pullback, primarily referring to those involving dozens of connections, is crucial in addressing the issue of spatial constraints at the drilling site. Nonetheless, this method does come with its own set of limitations. By analyzing and comparing various engineering examples, this paper aims to highlight the differences and technical challenges between multiple connectionspullback and traditional pullback methods in the context of horizontal directional drilling. This paper also proposes potential countermeasures, offering theoretical references and successful experiences for future projects of the same nature. The multiple connectionspullback method is suitable for application under stable formation conditions such as bedrock. Each process must be closely connected, and the suspension time of pullback should be minimized to ensure a successful construction process. When combined with methods such as pipelaying ship and support frames for pipe sending, the multiple connectionspullback method holds significant promise for widespread applications.